Client: Gosport Borough Council
Project: Forton Lake Footbridge
Completed: 2000
Value: £1.4 million
This architecturally designed 10 span Millennium footbridge is 180 metres
long, and incorporates a 20 metre long opening centre section.
The construction uses high quality white pre-cast concrete side and soffit
units, in-filled with reinforced concrete. The opening section was
fabricated from steel.
The scheme, which involved significant environmental measures,
was chosen by the DTI as a Demonstration Project for its Movement for Innovation
(M4I) construction industry initiative. |
| | |