19:02:2010
On course for a clean sheet

The £3m NORA (Nar Ouse Regeneration Area) utilities contract is for the installation of bulk utilities - fresh and foul water, gas, telecoms and electricity - to a brownfield site in Kings Lynn, Norfolk.
The project is being delivered by the NSP (Norfolk Strategic Partnership - Norfolk County Council, May Gurney and Mott MacDonald) on behalf of the Borough Council of Kings Lynn and West Norfolk in an innovative and efficient use of an existing framework contract.
The site had been home to some the most polluting heavy industries from the past, leaving a legacy of arsenic, lead, tar, low level radio-active phosphogypsum and asbestos to name but a few.

Despite all these challenges, the project team is pulling out all the stops to be ready for the grand opening at the end of May 2010.
With so many challenges and tight deadlines, the odd slip up could be forgiven. Yet the dedication and focus of the team has ensured that they have maintained a clean H&S record and no environmental incidents to date.
Raising the bar even higher, the have tasked themselves with the ambitious target of halving their carbon footprint.
Everything from electricity use in the office, liftshare and plant fuel use, to composting of food waste from the site compound is being approached with the same enthusiasm as the challenging ‘day job’.
Footnote: The project team is also responsible for the concurrent delivery of a £5.3m CIF (Community Infrastructure Fund) highway improvement scheme, again producing efficiencies to both clients through integrated delivery.